Multiple Choices
Answer (Choose 1 answer)
A team divided the application they were building into 4 parts and planning to build one part at a time. To build each part, they are planning to go through the steps of requirements, design, implementation, test, and deployment. Also, they are planning to complete each part fully with high fidelity. By fidelity we mean the completeness of the features implemented in each part. Based on this information, what type of model do you suggest they use for their software development process?
A. Iterative and Incremental
B. Incremental
C. Iterative