Multiple Choices
Answer (Choose 1 answer)
If a new requirement emerges once a Scrum project is running, it should be:
A. Automatically included in the work of the project
B. Automatically excluded and left until a later project or increment
C. Assessed for importance and, if sufficiently important to the business, included in the project, possibly displacing less important requirements
D. Put on the backlog for consideration by the wider group of stakeholders after the project has been completed