In Scrum projects, we plan to "learn as we go" because
A. It creates a better relationship between the developers and customer representatives
B. Many projects are evolutionary, and a better solution emerges this way
C. It is time-consuming to analyze everything at the beginning of a project
D. It prevents late delivery of the project