Kizspy Question: 39
(Choose 1 answer)
FOUVERAL OVA com
If you prototype the whole solution rather than only the most uncertain, high-risk, or complex portions, your
risk is
A. investing excessive effort in prototypes
B. distraction by details
C. pressure to release the prototype
D. unrealistic performance expectations