Kizspy Question: 52
(Choose 1 answer)
What is the Change Control Board (CCB)?
A. A group of stakeholders responsible for documenting project assumptions
B. A group that decides to approve or reject proposed changes for a specific project
C. A team of project managers tasked with managing project risks
D. A committee responsible for scheduling project milestones