Kizspy Question: 55
(Choose 1 answer)
How can risks be prioritized in project management?
A. By focusing on risks that are least likely to occur
B. By considering both the likelihood of occurrence and potential impact of risks
C. By ignoring potential impact and only considering likelihood
D. By assuming that all risks are equally important