Kizspy | Question: 51 (Choose 1 answer)
Which is NOT element of risk management?
A. Risk avoidance is one way to deal with a risk: don't do the risky thing.
B. Risk assessment is the process of examining a project to identify potential threats.
C. Risk control activities to manage the top-priority risks you identified.
D. Risk management planning produces a plan for dealing with each significant risk, including mitigation approaches, contingency plans, owners, and timelines.