Which of the following activities should be performed during the selection and implementation of a testing
tool?
i) Investigate the organisation's test process.
ii) Conduct a proof of concept.
iii) Implement the selected tool on a project behind schedule to save time.
iv) Identify coaching and mentoring requirements for the use of the selected tool.
A. i, ii, iii.
B. ii, iii, iv.
C. i, iii, iv.
D. i, ii, iv.