Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.

Cùng tham gia nhóm của FuOverflow trên Facebook https://www.facebook.com/groups/nvh2fuoverflow
PMG201c_FA24_PE2_412673
07/12/2024 7h30
EV = PV + CV???Request 3:
Risk 1: Poor Ticket Sales
- Probability: High (70%)
- Impact: High (Budgetary shortage jeopardizing success criteria).
Response Plan:
+ Mitigation: Launch an aggressive early-bird ticket campaign and use social media influencers to promote ticket sales.
+ Contingency: Reduce non-critical consumptions (e.g., decor costs) if sales remain below target.
Risk 2: Venue or Logistics Issues
- Probability: Medium (50%)
- Impact: High (Delays, cancellation, or compromised event quality).
Response Plan:
+ Mitigation: Have backup venues identified and arrange flexible contracts with vendors.
+ Contingency: Engage an experienced logistics coordinator and prepare for emergency adjustments.
Risk 3: Sponsor Withdrawal
- Probability: Low (30%)
- Impact: High (Significant budget impact).
Response Plan:
+ Mitigation: Secure multiple smaller sponsors to diversify funding sources.
+ Contingency: Prepare a secondary budget plan prioritizing critical elements.
Scoring System:
Probability: High (70%+), Medium (40-69%), Low (<40%).
Impact: High (Critical financial/operational loss), Medium (Moderate disruption), Low (Minor inconvenience).
Request 4:
Path 1: Start -> A -> B -> C -> G -> End
Duration: 4 + 3 + 2 + 6 = 15 weeks
Path 2: Start -> D -> B -> C -> G -> End
Duration: 5 + 3 + 2 + 6 = 16 weeks
Path 3: Start -> D -> E -> F -> G -> End
Duration: 5 + 4 + 2 + 6 = 17 weeks
Path 4: Start -> D -> H -> I -> End
Duration: 5 + 5 + 9 = 19 weeks
The critical path is the longest path, as it determines the minimum time required to complete the project.
Critical Path: Path 4 (Start -> D -> H -> I -> End) with a duration of 19 weeks.
Solutions to Shorten the Schedule by 3 Weeks
To reduce the schedule from 19 weeks to 16 weeks, we must focus on activities along the critical path (D, H, I). Below are three potential solutions:
- Reduce Activity Duration for "I" (H -> I):
+ Current Duration: 9 weeks
+ Proposed Change: Reduce by 3 weeks through crashing (e.g., adding more resources or parallelizing tasks where possible).
+ Impact: Critical path is reduced to 16 weeks.
- Reduce Activity Duration for "H" (D -> H):
+ Current Duration: 5 weeks
+ Proposed Change: Reduce by 2 weeks (e.g., by allocating additional resources) and reduce "I" by 1 week.
+ Impact: Critical path is reduced to 16 weeks.
- Fast-Track Activities "H" and "I":
+ Approach: Overlap tasks "H" and "I" partially to save 3 weeks. For example: Start "I" after 3 weeks of "H" instead of waiting for "H" to finish.
+ Impact: Critical path is reduced to 16 weeks without altering individual task durations.
Request 5: EV = PV + CV = 125,000 − 10,000 = 115,000
Cost Performance Index (CPI): CPI = EV / AC = 115000 / 120000 = 0.96
Schedule Performance Index (SPI): SPI = EV / PV = 115000 / 125000 = 0.92
Comments on Current Status:
- Schedule: Behind schedule (SPI < 1), indicating that less work has been completed than planned.
- Cost: Over budget (CPI < 1), meaning the project is spending more than expected for the achieved value.
Forecast: If current trends continue, the project will struggle to meet deadlines and exceed its budget.
Recommended Adjustments:
- Cost Control: Review and eliminate non-essential costs to improve CPI.
- Schedule Catch-up: Allocate additional resources or extend working hours to accelerate progress.
- Risk Management: Focus on mitigating potential high-probability risks like ticket sales and scene issues to prevent further disruptions.
sai đó, hồi đó làm vộiEV = PV + CV???
cho mình hỏi là PMG201c đề tài là chuẩn bị trước à? xem đề toàn thấy yêu cầu chứ ko thấy yêu cầu đề tàiPMG201c_FA24_PE2_412673
07/12/2024 7h30
minh tu chon de tai r lam docho mình hỏi là PMG201c đề tài là chuẩn bị trước à? xem đề toàn thấy yêu cầu chứ ko thấy yêu cầu đề tài
thi trên EOS sao mà lật tài liệu word được bạnCho mình hỏi là có thể chuẩn bị sẵn tài liệu trước sau đó dựa vào mà viết khi thi có được không?