PMG201c - FA 2024 - PE2
07/12/2024 7h30
 

Đính kèm

  • PMG201c_-_FA_2024_-_PE2_3165.webp
    PMG201c_-_FA_2024_-_PE2_3165.webp
    301.8 KB · Xem: 16,793
  • PMG201c_-_FA_2024_-_PE2_3165.webp
    PMG201c_-_FA_2024_-_PE2_3165.webp
    229.7 KB · Xem: 16,699
Request 1: Project Details
Project Name: Annual Charity Gala for Education
Purpose: To raise funds for underprivileged children’s education by organizing a memorable and high-profile charity gala.
Objectives:
- Raise $200,000 for the cause.
- Promote awareness about the importance of education for all.
- Build strong community and stakeholder engagement.
Customer and Sponsor:
- Primary Customer: A local non-governmental organization focused on children’s education.
- Sponsor: A consortium of corporate partners, local businesses, and humanitarians.
Success Criteria:
- Budgetary Goal: Achieving or exceeding the $200,000 fundraising target.
- Attendance: Attracting at least 300 guests, including corporate representatives, media, and influencers.
- Quality: Ensuring a consistent, engaging, and professionally executed event, reflected in post-event feedback surveys with a minimum satisfaction score of 90%.
- Awareness: Generating at least 50 media mentions and significant social media buzz during and post-event.
Project Constraints:
- Cost: Strict budget cap of $150,000 for organizing the event.
- Resources: Limited availability of professional event planning staff; dependence on volunteers and part-time workers.
- Quality: High expectations from sponsors and attendees, requiring top-tier execution.
Request 2: Current organizational Type: The project likely uses a functional organization where event management tasks are assigned to specialized departments (e.g., marketing for promotions, finance for budgeting).
Recommended Organizational Type: A matrix organization (preferably a strong matrix) should be applied for this project.
Reasons:
- Cross-functional collaboration: A matrix structure allows masters from different areas (marketing, logistics, finance) to work together, improving coordination and creativity.
- Clear authority: A project manager in a strong matrix ensures responsibility and prioritization of event goals over functional departmental priorities.
- Flexibility: The matrix allows resource optimization by drawing skill from multiple departments without overburdening one team.
 
Request 3:
Risk 1: Poor Ticket Sales
- Probability: High (70%)
- Impact: High (Budgetary shortage jeopardizing success criteria).
Response Plan:
+ Mitigation: Launch an aggressive early-bird ticket campaign and use social media influencers to promote ticket sales.
+ Contingency: Reduce non-critical consumptions (e.g., decor costs) if sales remain below target.
Risk 2: Venue or Logistics Issues
- Probability: Medium (50%)
- Impact: High (Delays, cancellation, or compromised event quality).
Response Plan:
+ Mitigation: Have backup venues identified and arrange flexible contracts with vendors.
+ Contingency: Engage an experienced logistics coordinator and prepare for emergency adjustments.
Risk 3: Sponsor Withdrawal
- Probability: Low (30%)
- Impact: High (Significant budget impact).
Response Plan:
+ Mitigation: Secure multiple smaller sponsors to diversify funding sources.
+ Contingency: Prepare a secondary budget plan prioritizing critical elements.
Scoring System:
Probability: High (70%+), Medium (40-69%), Low (<40%).
Impact: High (Critical financial/operational loss), Medium (Moderate disruption), Low (Minor inconvenience).
Request 4:
Path 1: Start -> A -> B -> C -> G -> End
Duration: 4 + 3 + 2 + 6 = 15 weeks
Path 2: Start -> D -> B -> C -> G -> End
Duration: 5 + 3 + 2 + 6 = 16 weeks
Path 3: Start -> D -> E -> F -> G -> End
Duration: 5 + 4 + 2 + 6 = 17 weeks
Path 4: Start -> D -> H -> I -> End
Duration: 5 + 5 + 9 = 19 weeks
The critical path is the longest path, as it determines the minimum time required to complete the project.
Critical Path: Path 4 (Start -> D -> H -> I -> End) with a duration of 19 weeks.
Solutions to Shorten the Schedule by 3 Weeks
To reduce the schedule from 19 weeks to 16 weeks, we must focus on activities along the critical path (D, H, I). Below are three potential solutions:
- Reduce Activity Duration for "I" (H -> I):
+ Current Duration: 9 weeks
+ Proposed Change: Reduce by 3 weeks through crashing (e.g., adding more resources or parallelizing tasks where possible).
+ Impact: Critical path is reduced to 16 weeks.
- Reduce Activity Duration for "H" (D -> H):
+ Current Duration: 5 weeks
+ Proposed Change: Reduce by 2 weeks (e.g., by allocating additional resources) and reduce "I" by 1 week.
+ Impact: Critical path is reduced to 16 weeks.
- Fast-Track Activities "H" and "I":
+ Approach: Overlap tasks "H" and "I" partially to save 3 weeks. For example: Start "I" after 3 weeks of "H" instead of waiting for "H" to finish.
+ Impact: Critical path is reduced to 16 weeks without altering individual task durations.
Request 5: EV = PV + CV = 125,000 − 10,000 = 115,000
Cost Performance Index (CPI): CPI = EV / AC = 115000 / 120000 = 0.96
Schedule Performance Index (SPI): SPI = EV / PV = 115000 / 125000 = 0.92
Comments on Current Status:
- Schedule: Behind schedule (SPI < 1), indicating that less work has been completed than planned.
- Cost: Over budget (CPI < 1), meaning the project is spending more than expected for the achieved value.
Forecast: If current trends continue, the project will struggle to meet deadlines and exceed its budget.
Recommended Adjustments:
- Cost Control: Review and eliminate non-essential costs to improve CPI.
- Schedule Catch-up: Allocate additional resources or extend working hours to accelerate progress.
- Risk Management: Focus on mitigating potential high-probability risks like ticket sales and scene issues to prevent further disruptions.
 
PMG201c_FA24_PE2_412673
07/12/2024 7h30
Request 3:
Risk 1: Poor Ticket Sales
- Probability: High (70%)
- Impact: High (Budgetary shortage jeopardizing success criteria).
Response Plan:
+ Mitigation: Launch an aggressive early-bird ticket campaign and use social media influencers to promote ticket sales.
+ Contingency: Reduce non-critical consumptions (e.g., decor costs) if sales remain below target.
Risk 2: Venue or Logistics Issues
- Probability: Medium (50%)
- Impact: High (Delays, cancellation, or compromised event quality).
Response Plan:
+ Mitigation: Have backup venues identified and arrange flexible contracts with vendors.
+ Contingency: Engage an experienced logistics coordinator and prepare for emergency adjustments.
Risk 3: Sponsor Withdrawal
- Probability: Low (30%)
- Impact: High (Significant budget impact).
Response Plan:
+ Mitigation: Secure multiple smaller sponsors to diversify funding sources.
+ Contingency: Prepare a secondary budget plan prioritizing critical elements.
Scoring System:
Probability: High (70%+), Medium (40-69%), Low (<40%).
Impact: High (Critical financial/operational loss), Medium (Moderate disruption), Low (Minor inconvenience).
Request 4:
Path 1: Start -> A -> B -> C -> G -> End
Duration: 4 + 3 + 2 + 6 = 15 weeks
Path 2: Start -> D -> B -> C -> G -> End
Duration: 5 + 3 + 2 + 6 = 16 weeks
Path 3: Start -> D -> E -> F -> G -> End
Duration: 5 + 4 + 2 + 6 = 17 weeks
Path 4: Start -> D -> H -> I -> End
Duration: 5 + 5 + 9 = 19 weeks
The critical path is the longest path, as it determines the minimum time required to complete the project.
Critical Path: Path 4 (Start -> D -> H -> I -> End) with a duration of 19 weeks.
Solutions to Shorten the Schedule by 3 Weeks
To reduce the schedule from 19 weeks to 16 weeks, we must focus on activities along the critical path (D, H, I). Below are three potential solutions:
- Reduce Activity Duration for "I" (H -> I):
+ Current Duration: 9 weeks
+ Proposed Change: Reduce by 3 weeks through crashing (e.g., adding more resources or parallelizing tasks where possible).
+ Impact: Critical path is reduced to 16 weeks.
- Reduce Activity Duration for "H" (D -> H):
+ Current Duration: 5 weeks
+ Proposed Change: Reduce by 2 weeks (e.g., by allocating additional resources) and reduce "I" by 1 week.
+ Impact: Critical path is reduced to 16 weeks.
- Fast-Track Activities "H" and "I":
+ Approach: Overlap tasks "H" and "I" partially to save 3 weeks. For example: Start "I" after 3 weeks of "H" instead of waiting for "H" to finish.
+ Impact: Critical path is reduced to 16 weeks without altering individual task durations.
Request 5: EV = PV + CV = 125,000 − 10,000 = 115,000
Cost Performance Index (CPI): CPI = EV / AC = 115000 / 120000 = 0.96
Schedule Performance Index (SPI): SPI = EV / PV = 115000 / 125000 = 0.92
Comments on Current Status:
- Schedule: Behind schedule (SPI < 1), indicating that less work has been completed than planned.
- Cost: Over budget (CPI < 1), meaning the project is spending more than expected for the achieved value.
Forecast: If current trends continue, the project will struggle to meet deadlines and exceed its budget.
Recommended Adjustments:
- Cost Control: Review and eliminate non-essential costs to improve CPI.
- Schedule Catch-up: Allocate additional resources or extend working hours to accelerate progress.
- Risk Management: Focus on mitigating potential high-probability risks like ticket sales and scene issues to prevent further disruptions.
EV = PV + CV???
 